NEW QUESTION # 15
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. A workflow can be triggered to inform the purchasing group.
  • B. The system automatically creates a new purchase requisition with the difference to the original quantity
  • C. The purchase order is updated automatically to match the new quantity while saving the project.
  • D. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)

Answer: C


NEW QUESTION # 16
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

  • A. The unit (for example, hour, day) of the field Normal Duration field of the activity
  • B. An activated Scheduling indicator in the control key of the internal processing activity
  • C. The relationships between activity elements
  • D. Whether the work for the internal activity is greater than its duration
  • E. The factory calendar in the work center used for the internal processing activity

Answer: A,B,E


NEW QUESTION # 17
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Investment profile
  • B. Settlement rule
  • C. Results analysis key
  • D. Costing sheet

Answer: D


NEW QUESTION # 18
The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false.

  • A. True
  • B. False

Answer: B


NEW QUESTION # 19
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

  • A. Set up the requirement date manually as February 5.
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days
  • C. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Answer: D


NEW QUESTION # 20
Which object is used to allocate the costs from a claim to the project structure?

  • A. WBS element
  • B. Claim
  • C. Network activity
  • D. Internal order

Answer: D


NEW QUESTION # 21
How can you grant individual authorization for WBS elements and networks?

  • A. Activate access control lists (ACL) for the project profile and the network profile
  • B. Define a user status to lock the business transaction Update Project.
  • C. Set the system status to "Lock Master Data".
  • D. Activate access control lists (ACL) for the user master record.

Answer: D


NEW QUESTION # 22
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

  • A. Enter February 10 as fixed date.
  • B. Enter an offset of 10 days to the start date of the activity.
  • C. Enter an offset of -18 days to the finish date of the activity.
  • D. Enter 10 days as duration.

Answer: A


NEW QUESTION # 23
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

  • A. Detailed planning for WBS
  • B. Unit costing for WBS
  • C. Easy Cost Planning (ECP) for WBS
  • D. Planning of overall values

Answer: D


NEW QUESTION # 24
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans are copied automatically to the sales order item.
  • B. Billing plans are used for revenue planning
  • C. Billing plans enable the billing process to be carried out
  • D. Billing plans are prerequisites for quotation creation

Answer: B


NEW QUESTION # 25
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

  • A. Assignment between material and standard network
  • B. A material master with sales views
  • C. A bill of material with sales views
  • D. A production order
  • E. Standard network with activities

Answer: A,B,E


NEW QUESTION # 26
You are working with networks and WBS elements. Which of the following statements applies

  • A. You have to maintain a network profile in the project profile
  • B. You can assign the network header to multiple WBS elements
  • C. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
  • D. You can reassign an activity from one network to another

Answer: C


NEW QUESTION # 27
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project profile
  • B. In the project version
  • C. In the project type
  • D. In the project definition of a standard WBS
  • E. In the operative WBS element

Answer: A,D,E


NEW QUESTION # 28
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.

  • A. At least one WBS element must be a billing element.
  • B. Revenue planning and billing must be activated in the corresponding network type.
  • C. The indicator "Project type" must be set to "Customer project".
  • D. A sales order item has to be assigned to each WBS element used for revenue planning.

Answer: A


NEW QUESTION # 29
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.

  • A. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
  • B. You can shorten the project mask even when there are existing projects.
  • C. You can use the same coding mask for standard projects and operative projects.
  • D. You can only use numbers for a project coding mask definition.

Answer: A,C


NEW QUESTION # 30
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.

  • A. Activity type
  • B. Duration
  • C. Work
  • D. Profit center

Answer: A,C


NEW QUESTION # 31
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. An MRP group must be assigned
  • B. The exact lot size procedure must be used
  • C. The procurement type of the material must be internal
  • D. The materials must allow sales order or project stock

Answer: B,C


NEW QUESTION # 32
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question

  • A. Sales order
  • B. Inquiry
  • C. Billing
  • D. Quotation

Answer: B,C


NEW QUESTION # 33
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

  • A. Saving a purchase order
  • B. Saving a supplier invoice
  • C. Saving a service entry shee
  • D. Saving a goods receipt

Answer: C,D


NEW QUESTION # 34
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates and latest dates are scheduled by forward scheduling.
  • B. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • C. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.

Answer: C


NEW QUESTION # 35
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. WBS elements
  • B. Sales order items
  • C. Project definition
  • D. Milestones

Answer: A,B


NEW QUESTION # 36
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions can be created automatically based on user status.
  • B. Project versions can be changed.
  • C. Project versions are mandatory for Milestone Trend Analysis (MTA).
  • D. Manually created project versions always require a project version profile.

Answer: B,C


NEW QUESTION # 37
Which planning method can prevent further rescheduling of activities?

  • A. Partial confirmation of activities
  • B. Capacity requirements activation
  • C. Capacity levelling
  • D. Workforce planning

Answer: B


NEW QUESTION # 38
......