API API-1184 Exam Overview:
| Certification Vendor: | American Petroleum Institute (API) |
| Exam Name: | API 1184 Pipeline Facility Construction Inspector Exam |
| Exam Number: | API-1184 |
| Exam Format: | Multiple-choice (single response), Computer-based testing (CBT), Closed-book |
| Certificate Validity Period: | 3 years |
| Related Certifications: | API 1169 Pipeline Inspector Certification |
| Exam Duration: | 180 minutes |
| Available Languages: | English |
| Real Exam Qty: | 120 (110 scored + 10 unscored pretest) |
| Recommended Training: | API 1184 Exam Preparation Training (Facility Inspector Courses) |
| Exam Registration: | API ICP Certification Portal |
| Sample Questions: | API API-1184 Sample Questions |
| Exam Way: | In-person computer-based testing at designated test centers |
| Pre Condition: | Work experience in pipeline facilities or related heavy industry fields (requirements vary by experience and education level; typically 1–5+ years depending on qualification path) |
| Official Syllabus URL: | https://www.api.org/products-and-services/individual-certification-programs/certifications/api1184 |
API API-1184 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Pipeline Facility Construction Inspection Fundamentals | - Facility construction overview
|
| Construction Quality and Technical Execution | - Coating and corrosion protection
|
| Safety, Environmental, and Regulatory Compliance | - Environmental protection
|
| Documentation and Project Turnover | - Inspection records
|
API Pipeline Facility Construction Inspector Sample Questions:
1. What is the purpose of corrective action in pipeline construction?
A) To prevent the discovery of nonconformances
B) To eliminate the cause of a nonconformance and prevent recurrence
C) To change the design of the pipeline facility
D) To increase the production speed
2. What is the purpose of an isolation block valve?
A) To regulate temperature in machinery
B) To isolate machinery for maintenance
C) To prevent equipment classification conflicts
D) To control the flow of gas
3. What is the primary purpose of API RP 1110?
A) To provide guidelines for pressure testing water pipelines
B) To offer guidance for pressure testing steel pipelines
C) To establish regulations for pipeline construction
D) To recommend materials for pipeline coatings
4. Which type of service is typically defined as critical in machinery installation?
A) Non-slam service
B) Critical service
C) Wet gas service
D) Ambient service
5. Which type of coupling obtains its flexibility from the flexing of an elastomeric element?
A) Elastomeric coupling
B) Disk coupling
C) Gear coupling
D) Flexible-element coupling
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: B | Question # 3 Answer: B | Question # 4 Answer: B | Question # 5 Answer: A |

We're so confident of our products that we provide no hassle product exchange.


By Geraldine