NEW QUESTION # 25
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By requiring details at the start
  • B. By allowing a lot of detail at the start
  • C. By preventing the analysis of details at the start
  • D. By avoiding too much detail at the start

Answer: C


NEW QUESTION # 26
Which statement explains the PRINCE2 Agile behavior of 'exploration'?

  • A. It displays the progress rate to everyone using burn-down charts
  • B. It uses the most effective channel to communicate information
  • C. It seeks out feedback collaboratively from project stakeholders
  • D. It empowers the project management team at the delivery level

Answer: C


NEW QUESTION # 27
What is the definition of a timebox?

  • A. A period where work is carried out to achieve a goal
  • B. A regular event that looks at how processes can be improved
  • C. A description of the rate of progress a team is making
  • D. A tool to write a requirement in the form of who, what and why

Answer: A


NEW QUESTION # 28
Which statement about the 'be on time and hit deadlines' target is CORRECT?

  • A. It ensures that the level of quality is protected
  • B. It is achieved by keeping the delivery teams stable
  • C. It helps with planning dependencies within a project
  • D. It allows change to be handled dynamically

Answer: C


NEW QUESTION # 29
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It gives confidence on the progress of the project
  • B. It is achieved by allowing enough time for testing
  • C. It delivers the early realization of benefits
  • D. It is achieved by using the same team members

Answer: C

Explanation:
Reference:
%20level%20is%20met


NEW QUESTION # 30
Which is a typical characteristic of 'business as usual' work?

  • A. It is delivered by an established team
  • B. It is executed by program management
  • C. It requires a specific dedicated project manager
  • D. It is delivered by a temporary team

Answer: A


NEW QUESTION # 31
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. T-shirt sizing
  • B. Trading
  • C. Rationalism
  • D. Visioning

Answer: C


NEW QUESTION # 32
Which is often used during a retrospective to capture lessons?

  • A. A Glad! Sad! Mad! board
  • B. A Kanban board
  • C. A Gantt chart
  • D. A burn chart

Answer: A


NEW QUESTION # 33
Which statement about velocity is CORRECT?

  • A. It tracks the time and cost of a timebox
  • B. It describes how much work is getting done
  • C. It is shown by the ideal line on a bum-down chart
  • D. It is based on the concept of rationalism

Answer: B


NEW QUESTION # 34
What does velocity typically measure?

  • A. The speed that a minimum viable product is created
  • B. The number of timeboxes completed
  • C. Work packages completed by the team
  • D. The rate of progress the team is making

Answer: D


NEW QUESTION # 35
To help with prioritization, what is MOST important when understanding the difference between scope and quality?

  • A. Defining non-functional requirements before functional requirements
  • B. Differentiating functional from non-functional requirements
  • C. Creating non-functional requirements with user stories
  • D. Combining functional and non-functional requirements

Answer: B


NEW QUESTION # 36
Which is a purpose of the 'controlling stage' process?

  • A. To report stage progress to the project board
  • B. To draft the plan for the next stage's work
  • C. To establish whether the project is complete
  • D. To execute and deliver the project product

Answer: A

Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control


NEW QUESTION # 37
In Lean Startup, what is based on the concept of 'learn the most with the least effort'?

  • A. A set of criteria to determine whether work can be started
  • B. A minimum viable product
  • C. A measurement of lead times
  • D. A structured, timeboxed event

Answer: B


NEW QUESTION # 38
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

  • A. How to select which Agile framework should be favoured
  • B. How to adapt the PRINCE2 management products
  • C. How to calculate the project budget and cost tolerance
  • D. How to decide whether PRINCE2 is appropriate

Answer: B


NEW QUESTION # 39
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 1 and 4
  • B. 1 and 2
  • C. 3 and 4
  • D. 2 and 3

Answer: A


NEW QUESTION # 40
Which is a purpose of the 'managing product delivery' process?

  • A. To establish and deliver the project communications to the wider organization
  • B. To plan the delivery of the products before committing to significant expenditure
  • C. To delegate day-to-day management of the project to the project manager
  • D. To agree on what is required for accepting, executing and delivering project work.

Answer: D


NEW QUESTION # 41
Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT?

  • A. It creates a shared ownership of goals
  • B. It uses the most effective channel to communicate
  • C. It allows many small learnings to accumulate over time
  • D. It allows the delivery team to decide how best to get the job done

Answer: A


NEW QUESTION # 42
Which is a purpose of the plans theme?

  • A. To control any approved changes to the baseline
  • B. To identify any deviations from the project's objectives
  • C. To monitor actual achievements against those planned
  • D. To communicate the approach for delivering products

Answer: D


NEW QUESTION # 43
Which is a purpose of the quality theme?

  • A. To determine how the means of delivering products is communicated
  • B. To evaluate whether the project continues to be achievable
  • C. To assess any potential improvements to a product
  • D. To define the specific conditions that enable a product to be usable

Answer: B


NEW QUESTION # 44
Which statement about the waterfall methodology definition is CORRECT?

  • A. It has distinct goals for each stage of development
  • B. It states that deadlines should not be moved
  • C. It promotes the use of experiments carried out in a scientific way
  • D. It is a behavior that involves making things transparent

Answer: A


NEW QUESTION # 45
How should product-based planning be used as part of PRINCE2 Agile?

  • A. To plan by focusing on the features required
  • B. To create the project plan using empiricism
  • C. To enable team planning to be predictive
  • D. To track progress against the team plan

Answer: A


NEW QUESTION # 46
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It ensures that the level of quality is protected
  • B. It results in the earth delivery of a minimum viable product
  • C. It is required in order to allow the team to self-organize
  • D. It will lead to a lower cost of ownership

Answer: C


NEW QUESTION # 47
Which statement about the 'embrace change' target is CORRECT?

  • A. It reduces testing in order to meet deadlines
  • B. It minimizes the time needed to train a new team member
  • C. It encourages the customer to raise new ideas
  • D. It reduces the planning of dependencies between projects

Answer: C


NEW QUESTION # 48
How does PRINCE2 Agile describe Scrum?

  • A. Scrum is the most well-known agile framework
  • B. Scrum is a project management framework
  • C. Scrum is agile and agile is Scrum
  • D. Scrum is an IT method

Answer: A


NEW QUESTION # 49
......


Earning the PRINCE2 PRINCE2-Agile-Foundation (PRINCE2 Agile Foundation) certification demonstrates your knowledge and understanding of the PRINCE2 Agile methodology, which is becoming increasingly popular in project management. PRINCE2 Agile Foundation certification is recognized globally and is highly valued by employers in various industries. It also provides a solid foundation for further training and certification in PRINCE2 Agile at the Practitioner and Professional levels. Whether you are a project manager, team member, or interested in project management, the PRINCE2 PRINCE2-Agile-Foundation (PRINCE2 Agile Foundation) Exam is a great way to enhance your skills and advance your career.

 