BICSI Registered Communications Distribution Designer - RCDD v15 Sample Questions:
1. In a contiguous properly environment (e. g., where campus backbone cables exist), which two of the following are CRITICAL factors to understand for maintenance and growth purposes? (Select two options.)
A) Cable composition
B) Familiarity with the routes and spaces (proper record keeping)
C) Cost analysis of the value of capex and capex models
D) Not able to determine the working capacity versus spare cable capacity
E) Fill ratio
2. Conducted coupling may affect electronic devices primarily through which two of the following means'? (Select two options.)
A) Output signal lines
B) inductive coupling (by magnetic fields)
C) Optical signal lines
D) Input signal lines
E) Capacitive coupling (by electric fields)
3. Which of the following is TRUE for tele communications spaces?
A) Close proximity to water service is desired so consider locating the ER in the pipe chase.
B) Maintain aim (3.28 ft) clearance between equipment and plumbing fixtures such as mop sinks
C) Relative humidity snail be maintained at 40% ± 5%.
D) Plumbing piping not related to the support of the space should not pass through the space.
4. As a project manager, what should the FINAL task be at of the end of each project?
A) A costing and billing review
B) Delivery of the final documentation
C) A lessons learned meeting
D) A sign off meeting with the owner
5. For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a
A) SoW.
B) spare ad sheet
C) worksheet
D) database
Solutions:
| Question # 1 Answer: B,C | Question # 2 Answer: B,E | Question # 3 Answer: D | Question # 4 Answer: C | Question # 5 Answer: C |

We're so confident of our products that we provide no hassle product exchange.


By Don