SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 Sample Questions:
1. In modeling in-house production using SAP ECC, bills of material (BOM) are to be recorded in the system. On which business levels can you create a BOM? (Choose two.)
A) At the company code level
B) At the plant level
C) At the business area level
D) At the client level
2. What options for selecting a routing exist when creating a production order?
(Choose three.)
A) Manual selection
B) Selection on the basis of the routing number in the material master for the material to be produced
C) Selection on the basis of the production control profile
D) Automatic selection, controlled via settings in Customizing
3. Which one of the following scheduling types cannot be assigned as default to an order type (production order)?
A) Midpoint
B) Forward
C) Backward
D) Only capacity requirements
4. An enterprise wants to absorb the uncertainty caused by fluctuating demand for a finished product by means of a buffer variable in SAP ECC. They suggest a dynamic safety stock.
What specifications are used to calculate the dynamic safety stock?
A) The average daily demand and the safety time
B) The static safety stock and a material forecast
C) The static safety stock per day and the safety time
D) The average daily demand and the desired days supply
5. A user you advise wishes to transfer variable process instructions for automated processing directly to certain work centers and machines in the production department (for example, feed speed, pressing pressure, dry temperature). The user also wishes to receive variable as-is messages (such as actual quantities, actual times) from these work centers and machines and to process these messages for feedback concerning production orders. Which of the following options would you recommend to implement these requirements?
A) SAP Business Intelligence (BI)
B) Execution Steps (XSteps) and process messages
C) SAP Application Link Enabling (ALE)
D) Plant data collection (PP-PDC) interface
Solutions:
| Question # 1 Answer: B,D | Question # 2 Answer: A,C,D | Question # 3 Answer: A | Question # 4 Answer: D | Question # 5 Answer: B |

We're so confident of our products that we provide no hassle product exchange.